This schedule is tentative and subject to change.
· April 7th – Begin construction of west side of roadway south and new watermain south of Market Place/Andy Avenue intersection
· May 7th - Begin construction on east side near at Old Kilgore Road. Includes culvert widening and storm sewer installation
· May 22th - Begin roadway widening on the east side, south of Andy Avenue
· September 1st - All lanes open to traffic
· September 29th - Begin final landscaping, restoration, new streetlights and utility relocation
· November 15th – Project completion
Construction Contacts
The City of Portage is committed to communicating with all property owners along South Westnedge Avenue and adjacent neighborhoods during construction to address issues related to the project. If you are interested in receiving update on the construction please contact city staff. For immediate assistance during the construction project the contracts are:
City Project Manager: W. Christopher Barnes, City Engineer 269-329-4422 barnesc@portagemi.com
Project Resident Engineer: Dan Dombos, Abonmarche Consultants 269-927-2295 ddombos@abonmarche.com
Contractor: Greg Bruner, Peters Construction, 269-345-1145 gbruner@petersconstruct.com